Clean Car | Construction Update
- Customer Care

- Mar 19, 2020
- 1 min read
Henke Excavating
Pouring curbs around the building
Also started framing around the pay station
Removed some additional curb
Jos. F Becker, Inc.
The masonry contractor looking to be completed this week, but due to weather they couldn’t.
They are working on the dumpster pad, and wrapping the steel columns
Car Wash Contractor
Are working on the tank room and conveyor system this week
Federal Steel
They have started installing the steel, they will return next week
B & M Construction
Have completed the towers and windows, installed doors and are working on soffits
Will return Monday to start drywall and Taping
EIF contractor
They have completed about 1/3 of the building's foam eaves






















Comments