Henke Excavating

  • Forming curbs sched to pour this week

  • Drilling the holes and pouring the concrete for the steel contractor

Jos. F Becker, Inc.

  • Masonry contractor continuing to lay brick.

  • Due to the weather this week we have had some issues

Car Wash Contractor

  • Are working on the tank room and conveyor

Federal Steel

  • To deliver the steel this week

B & M Construction

  • Carpenters have started but due to the weather it’s been a slow start

  • We have 8 carpenters onsite working interior and, on the towers looking to complete them by Monday

  • Working over the weekend

  • We have boarded up the building to continue working inside the building