Clean Car | Construction Report
- Customer Care

- Feb 28, 2020
- 1 min read
Henke Excavating
Pouring foundations for steel
Drilling the holes and pouring the concrete for the steel contractor
We had a couple of loads of stone delivered this morning
Jos. F Becker, Inc.
Masonry contractor continuing to lay brick.
Due to the weather this week we have had some issues
Car Wash Contractor
Are working on the tank room and conveyor this week
Federal Steel
To deliver the steel this week
B & M Construction
Carpenters have started but due to the weather it’s been a slow start
Will return Monday