B & M Construction

  • Carpenters to continue to work on both towers and interior

  • Has started working on drywall and taping

  • Will continue taping over the weekend

Jos. F Becker, Inc.

  • Masonry contractor cond. to stonework and brickwork next week

  • They are looking to start removing all their equipment off site

Federal Steel

  • Are continuing to weld the remaining steel, looking to be completed next week

Roofing Contractor

  • Completed the TPO roofing, tower roofing material will ship from Chicago 3-25

  • They have started the flat metal roofing today and will continue to work on it next week.

Norman Electric

  • Electrician onsite working on cameras and rough electrical, and inside the tank room

  • Also working on the towers

Plumbing Contractor

  • Running water line for interior and will continue to work in the equipment room

  • Will start the gas lines next week.

Car Wash Contractor

  • To continue working on the tunnel panel, tank room, and equipment room

Henke Excavating

  • Removing the existing curbs

  • Pouring curbs

Storefront contractor

  • Looking to install the window frames and will start on the glass late next week

EIFs contractor

  • Will continue to work on the foam eaves, weather permitting