Clean Car | Construction Progress
- Customer Care

- Mar 26, 2020
- 1 min read
B & M Construction
Carpenters to continue to work on both towers and interior
Has started working on drywall and taping
Will continue taping over the weekend
Jos. F Becker, Inc.
Masonry contractor cond. to stonework and brickwork next week
They are looking to start removing all their equipment off site
Federal Steel
Are continuing to weld the remaining steel, looking to be completed next week
Roofing Contractor
Completed the TPO roofing, tower roofing material will ship from Chicago 3-25
They have started the flat metal roofing today and will continue to work on it next week.
Norman Electric
Electrician onsite working on cameras and rough electrical, and inside the tank room
Also working on the towers
Plumbing Contractor
Running water line for interior and will continue to work in the equipment room
Will start the gas lines next week.
Car Wash Contractor
To continue working on the tunnel panel, tank room, and equipment room
Henke Excavating
Removing the existing curbs
Pouring curbs
Storefront contractor
Looking to install the window frames and will start on the glass late next week
EIFs contractor
Will continue to work on the foam eaves, weather permitting