Did 6 test pits in the detention area for the engineer to determine suitability for retaining wall footers


Benched back pond per plans

Site was very saturated. There was 2.75” of rain in the rain gauge from 11-27 to the morning of 12-2.


With the TDOT meeting has being moved to December 13th, Pernell Excavating will most certainly have a demobilization and remobilization as a result.