top of page

Pure Clean | Construction Update

  • Writer: Customer Care
    Customer Care
  • Nov 22, 2019
  • 1 min read

Pernell Excavating

  • Continued with site grading

  • Started rock hammering in scattered places for grading

  • Moved usable stockpile to build up by rear entry

  • Started detention pond excavation

Collier’s Engineering

  • Onsite to observe proof rolling of rear entrance

Northstar Construction- Electrical Division

  • Met with power company to establish transformer location

  • Met with power company to establish temporary power location

General Items

  • Relocated office trailer per power company’s recommendation and allow grading to continue

  • After storm submittal review, the engineers notes mentioned the TDOT design change which can affect some elevations. This has put a hold on submittals for this section which is affected by the meeting on 12-13-19 with TDOT. Once resolution is obtained and design is finalized then submittal process will resume on this section in order to complete the storm installation for the site.


Comments