Pure Clean | Construction Update
- Customer Care

- Nov 22, 2019
- 1 min read
Pernell Excavating
Continued with site grading
Started rock hammering in scattered places for grading
Moved usable stockpile to build up by rear entry
Started detention pond excavation
Collier’s Engineering
Onsite to observe proof rolling of rear entrance
Northstar Construction- Electrical Division
Met with power company to establish transformer location
Met with power company to establish temporary power location
General Items
Relocated office trailer per power company’s recommendation and allow grading to continue
After storm submittal review, the engineers notes mentioned the TDOT design change which can affect some elevations. This has put a hold on submittals for this section which is affected by the meeting on 12-13-19 with TDOT. Once resolution is obtained and design is finalized then submittal process will resume on this section in order to complete the storm installation for the site.
















Comments