Pure Clean | Construction Update
- Customer Care
- Dec 6, 2019
- 1 min read
Pernell Excavating
Continued with site grading
Dug detention area to grade
Hauled off spoils from grading
Removed phone pole
Removed old sign
Installed culvert at the south entry
General Items
Had field engineer onsite to observe detention basin soil for foundation recommendations
Worked on the pricing of proposed options for detention basin foundation undercutting based on the field engineer’s recommendation
Pernell demobilized on 12-4 at the end of the day for 2 weeks
Scheduled work 12/9 to 12/13:
No work is scheduled until TDOT and/or building pad and/or detention basin undercutting is resolved