Pure Clean | Construction Update

  • Writer: Customer Care
    Customer Care
  • Dec 6, 2019
  • 1 min read

Pernell Excavating

  • Continued with site grading

  • Dug detention area to grade

  • Hauled off spoils from grading

  • Removed phone pole

  • Removed old sign

  • Installed culvert at the south entry

General Items

  • Had field engineer onsite to observe detention basin soil for foundation recommendations

  • Worked on the pricing of proposed options for detention basin foundation undercutting based on the field engineer’s recommendation

  • Pernell demobilized on 12-4 at the end of the day for 2 weeks

Scheduled work 12/9 to 12/13:

  • No work is scheduled until TDOT and/or building pad and/or detention basin undercutting is resolved